YARRA VALLEY WATER – MAINS RENEWAL PROGRAM

Project Start Date

December 2015

Project Completion Date

December 2022

Client

Yarra Valley Water

Comdain's Role

Principal Contractor

Value Range Category

$10m - $50m

Location

Victoria

Capabilities

Renewals Water & Wasterwater

Design and Construct water mains identified for renewal by Yarra Valley Water

Works Undertaken

  • The renewals program is a self-preform design and construct program of works for approximately 12km of reticulation Water Main Renewal per year over the life of the contract.
  • Construction method is determined based on range of criteria including cost, community impact and location. Techniques used include open cut, pipe cracking, directional drill and pipe relining.

Highlights & Innovations

  • Delivered 2017/18 program works plus additional 4kms (16kms in total) to assist Yarra Valley Water achieve annual targets.